Tech, ExplainedEnterprise SaaS and software
Part

Project portfolio management (PPM)

Which projects get the money.

INSIDE: PROJECT MANAGEMENT SOFTWAREHOW IT WORKS · CHOOSING NEXT YEAR'S PROJECTS AT AN INSURER IN MUMBAI60 proposalsask for ₹180crore in total;the budgetis ₹100 croreEach is scoredagainst threegoals: fasterclaims,online sales,IRDAI rules4 projectsrequired byIRDAI's rules(₹25 crore) arefunded firstThe 19highest-scoringothers (₹74crore) fill therest; 37 waitfor next yearA staffingcheck finds 28data engineersfor 40 needed,so 1 projectmoves to thethird quarterEach quarter,spending iscompared withthe plan; aproject 40% overis reviewed andcut backALSO TALKS TOFinancial planning and analysis (FP&A)↗ FINANCE AND ACCOUNTING SOFTWAREInternal talent marketplace↗ HR TECHNOLOGYINSIDE: PROJECT MANAGEMENT SOFTWAREHOW IT WORKS · CHOOSING NEXT YEAR'S PROJECTS AT ANINSURER IN MUMBAI60 proposals ask for ₹180crore in total; thebudget is ₹100 croreEach is scored againstthree goals: fasterclaims, online sales,IRDAI rules4 projects required byIRDAI's rules (₹25 crore)are funded firstThe 19 highest-scoringothers (₹74 crore) fillthe rest; 37 wait fornext yearA staffing check finds28 data engineersfor 40 needed, so1 project moves tothe third quarterEach quarter, spending iscompared with the plan; aproject 40% over isreviewed and cut backALSO TALKS TOFinancial planning and analysis (FP&A)↗ FINANCE AND ACCOUNTING SOFTWAREInternal talent marketplace↗ HR TECHNOLOGYINSIDE: PROJECT MANAGEMENT SOFTWARE · CHOOSINGNEXT YEAR'S PROJECTS AT AN INSURER IN MUMBAI60 proposals ask for ₹180 crore in total;the budget is ₹100 crore↓Each is scored against three goals:faster claims, online sales, IRDAI rules↓4 projects required by IRDAI's rules (₹25crore) are funded first↓The 19 highest-scoring others (₹74 crore)fill the rest; 37 wait for next year↓A staffing check finds 28 data engineersfor 40 needed, so 1 project moves to thethird quarter↓Each quarter, spending is compared withthe plan; a project 40% over is reviewedand cut backALSO TALKS TOFinancial planning and analysis (FP&A)↗ FINANCE AND ACCOUNTING SOFTWAREInternal talent marketplace↗ HR TECHNOLOGY
Inside project management software, PPM takes an insurer's 60 proposals asking for ₹180 crore, funds four required projects and the 19 highest-scoring others within a ₹100 crore budget, and checks spending every quarter.
opens a page inside this one a page in the same scene a page in another scene a concept page a label only, with no page

Project portfolio management (PPM) is software with which a large company decides which projects to fund and staff, and then tracks those projects against its strategy. A portfolio here means all the projects a company runs or is asked to run. PPM is part of project management software, one level higher: project management plans how to do one project, and PPM decides which projects to do at all.

It works in a yearly cycle, with quarterly checks. First, teams submit proposals. Each proposal states its cost, its expected benefit, its risk and the people it needs. Second, the company scores each proposal against its goals for the year. Third, it picks the best set of projects that fits within the budget. Fourth, it checks whether it has enough people with the right skills. Then, every quarter, it compares each project's spending and progress with the plan, and it stops or changes projects that are going badly.

Imagine the IT department of a general insurance company in Mumbai, planning next year's work. It receives 60 proposals, which ask for ₹180 crore in total. Its budget, set in the company's financial planning and analysis (FP&A) software, is ₹100 crore. Each proposal is scored against three goals: settling claims faster, selling more policies online, and meeting the rules of IRDAI, the insurance regulator. Four projects are needed to meet IRDAI's rules. They cost ₹25 crore, and they are funded first, whatever their score. PPM then ranks the other 56 by score for each rupee. The 19 highest fit into the next ₹74 crore. The remaining 37 proposals wait for next year.

Next comes the staffing check. The 23 chosen projects need 40 data engineers, but the department has only 28. So one project moves to the third quarter, when another project ends and its engineers become free. Some companies find people for such gaps through an internal talent marketplace, which matches staff whose project has ended to new projects.

In the second quarter, one project has spent 40% more than planned, and it is far behind. PPM shows this on the leadership's dashboard. The leadership reviews the project and cuts its scope. Without PPM, each team would push its own projects, and the company would not see the whole set together. Each funded project then runs as a detailed plan in project management software.

Tech, Explained is a part of ingrid.fyi. Every page explains one piece of technology in plain words.